Infrastructure - industry
Overall Project / Works:
- Location of Works: Phu Minh - Soc Son - Ha Noi.
- Scale works: Total factory area of 62,000 m2, including main building block and 12 workshops, Hall Hall, Canteen. Ancillary items such as kindergarten, clinic, staff collective ...
- Investor: Factory Z125 - Ministry of Defense.
- Total investment: 215.000 million VND.
Range of Ngoc Xanh construction:
- Scope of the tender package: Construction of new molded houses, medical home. Improving infrastructure, gates, access roads to factories, yards, gardens ...
- Value of the tender package: 42.125 million VND.
- Construction time: June 2015 - April 2017.
Overall Project / Works:
- Location of Works: An Khanh, Hoai Duc - Hanoi.
- Scale works: Pavement area and sidewalks are 33ha, the total length of the roads is 1,520m, the road cross section is 13-15m.
- Investor: Phuc Ha Industrial Park Infrastructure Investment and Development Joint Stock Company.
- Total investment: 2.800.000 million VND.
Range of Ngoc Xanh construction:
- Scope of the tender package: Construction of roads, rainwater and waste water drainage from line 1 to line 4.
- Value of the tender package: 14.988 million VND.
- Construction time: October 2014 - May 2015.
Overall Project / Works:
- Location of Works: CT 21-B Viet Hung New Urban Area, Long Bien District, Hanoi.
- Scale works: The total area of land is 11,700 m2, building 4 blocks of apartment building from 8 to 18 floors.
- Investor: Thien Huong Company Limited.
- Total investment: 760.000 million VND.
Range of Ngoc Xanh construction:
- Scope of the tender package: Construction of the entire project, making temporary internal roads. Testing piles. Executing the project.
- Value of the tender package: 5.420 million VND.
- Construction time: November 2015 - March 2016.